Monday 6th October We make up the final 8 gable panels (lots of work in them) and are now ready to stand them up once the scaffolding has been moved over from the Barn. This may take a few days so be patient with us!
Tuesday 7th October Jonathan returns to the site and he and Gus set about protecting the panels with breathable membrane and then covering them to stop the worst of the rain affecting them.
Wednesday 8th October David McKenzie arrives to drop the scaffold at the barns, hoping to errect on the semis towards the weekend.
Friday 10th October The scaffolding is partially erected around the two houses but, for a number of reasons, it is unlikely that we will do too much more until next Wednesday.