Monday 9th MarchNeil makes a start on the tiling in No.6 - begining with the floor tiles in the kitchen. | Monday 9th MarchThe shower room walls are completed and the floor is screeded in preparation for the 'laid to fall' shower to be tiled later in the week. |
|
Tuesday 10th MarchThe tiler progresses from the kitchen to the utility room. | Tuesday 10th MarchOutside the roofers return to complete the leadwork on the chimney of No.6. |
|
Tuesday 10th MarchBrian & Shug complete the blockwork on the walls - hooray! | Tuesday 10th MarchAnd add more scratch coat on the front of the house (note also the new cills on the upper windows). |
|
Tuesday 10th MarchFinally, inside Jerry & John spend the day completing the upper floor wiring circuits in No.6 - we now have working lights in all rooms upstairs. | Wednesday 11th MarchNeil lays more tiles and starts grouting the kitchen floor with black grout - looks very smart. |
|
Wednesday 11th MarchJohn & Jerry complete the upper floor power circuit and start on the room thermostats. | Thursday 12th MarchMore tiles, more grout, more sockets, more light switches. Meanwhile outside the builders complete the scratch coat on the front of the houses and the blocks on the second chimney are drying nicely - should be able to fit the cap and pot tomorrow. |
|
Friday 13th MarchBrian takes advantage of some fine weather to scratch coat a chimney. | Friday 13th MarchNeil tiles the upstairs bathroom and finishes laying the tiles in the hall and under stairs cupboard. |
|
Friday 13th MarchFinally, we take delivery of the kitchen for No.6 from Howdens. The joiners have been delayed a further week on the Barns, but fitting the kitchen will be first job for them a week on Monday! | |
|