Monday 1st DecemberIn our absence the joiners complete the battening of the ground floor of both houses. | Tuesday 2nd DecemberJerry gets started on the consumer units. |
|
Wednesday 3rd DecemberThe builders dig a trench and bury the conduit for the electricity cables. | Wednesday 3rd DecemberAlso, the roofers return to finish the lead valley gutter and start the last of the slates. |
|
Thursday 4th DecemberA landmark day as we get the electricity connected and the meters installed in the houses. | Thursday 4th DecemberThis is the hole outside the houses where the mains connection was made by SSE. |
|
Friday 5th DecemberJoan's birthday! Also, Pete from Earthwise returns to lay the under floor heating on the upper floors of both houses, whilst Jerry & John carry on with the wiring. | |
|