Monday 17th NovemberAn early start as the roofing contractors load the slates on to the scaffold with the help of a fork lift. | Monday 17th NovemberAfter sorting and grading the slates and preparing the lead vallies, by mid-afternoon the roofers have made a good start on the slates on the back roof of No. 5. |
|
Tuesday 18th NovemberInside, we finish the fireproof walls between the houses whilst outside the slaters make great progress on the back and front of the roof. | Wednesday 19th NovemberWe take delivery of 140 sheets of 50mm rigid insulation and while we get them inside the slaters crack on with the roof. |
|
Wednesday 19th NovemberGus & Jerry then start fitting the rigid insulation sheets to the outside walls while Johnothan carries on stuffing the kit with 100mm glass fibre insulation. | Thursday 20th NovemberThe slating at the front of the house is nearly complete. |
|
Friday 21st NovemberBrian makes a start on the lead work for the gutter in the rear vally. | Friday 21st NovemberInside we complete the insulation of the outside walls and stuff the coombes with high quality wool insulation (FrameTherm 35). |
|
| |
|