Monday 4th MayPete from EarthEnergy (aka Earthwise) starts bright and early on plumbing in the heating system in No.5. | Monday 4th MayThe doors are almost all hung and Kevin is here fitting the door catches to the No.2 bedroom. |
|
Tuesday 5th MayNeil returns to do the kitchen wall (& window surround) tiles in No 6. | Tuesday 5th MayWe have running water!! We finally get to switch on the water in No.5 and find a couple of leaks, but they are soon fixed and we can now enjoy a cup of tea and the use of our own toilet! Progress. |
|
Wednesday 6th MayDespite a few hicupps we get the first heat pump up and running and heating the domestic hot water % buffer tank for the underfloor heating. | Wednesday 6th MayOutside the contractors ignore the rain and manage to complete the disposal of the last of the spoil (17 loads at the last count) and start fitting the block pavoirs. |
|
Thursday 7th MayBrian makes a start on re-building the wall on one side of the entrance to the road. | Friday 8th MayThe first wall nears completion. |
|
| |
|