Week 2 - Foundations
Monday 18th August
The Accumix lorries arrive on site before 9.00 a.m. and get as close to the back corner of the foundations as possible.
Monday 18th August
Many hands make quick founds! The joiners join in to spread the concrete and the first 9 tonnes are down in less than an hour.
Monday 18th August
The founds are completed before mid-day and are starting to set by the close of play.
The builders will be back on Thursday morning to start on the blockwork.
Wednesday 20th August
We get a delivery of concrete blocks - 924 in all (21 x 44) ready for the builders tomorrow.
Thursday 21st August
Heavy and persistent rain curtails work on the site - we will hope for better weather next week!!
Home
Plans
The Site
Wk 1 - Trenches
WK 2 - FOUNDATIONS
Wk 3 - Underbuilding
Wk 4 - Slab Prep
WK 5 - FLOOR SLAB
Wk 6 - Nothing
Wk 7 - GF Panels
Wk 8 - Floor Joists
Wk 9 - FF Panels
Wk 10 - FF Panels
Wk 11 - Trusses
Wk 12 - Sarking
Wk 13 - Dormers
Wk 14 - Roof Prep
Wk 15 - Roofing
Wk 16 - FF Battens
Wk 17 - Electrics
Wk 18 - Wiring
Wk 19 - Upper Floor
WK 20 - Upper Floor
Wk 21 - Blockwork
WK 22 - Strapping
Wk 23 - Plasterboard
WK 24 - Chimneys
Wk 25 - Stairs
Wk 26 - Tape & Fill
Wk 27 - 2nd Fix
Wk 28 - 2nd FIX
Wk 29 -Tiling
Wk 30 - Harling
Wk 31 - Kitchen
Wk 32 - All Sorts
Wk 33 - Water&Drains
Wk 34 - Finishings
Wk 35 - Landscaping
Wk 36 - Landscaping
Wk 37 - Heating
Wk 38 - Almost There
Wk 39 - FINISHING #6