Monday 8th SeptemberBrian and Shug lay out the insulation panels. | Monday 8th SeptemberRooms, walls and fixed appliances are marked out on the panels (so that the under floor heating pipes are not run in these areas). |
|
Monday 8th SeptemberWire mesh is then cut and placed on the insulation panels in readiness for the UFH pipes to be fitted tomorrow. | Tuesday 9th SeptemberPeter from Earthwise arrives and gets to work on the manifolds and under floor heating pipes. |
|
Tuesday 9th SeptemberDespite some heavy rain in the afternoon all the pipes are down, the system is pressurised and one house has the spacers fitted under the wire mesh ready for the concrete floor to be laid in the morning. | Wednesday 10th SeptemberThe Accumix lorry arrives bright and early (well early anyway) and soon the slabs are taking shape. |
|
Wednesday 10th SeptemberBy the end of the day the concrete slabs are setting and Tom & Brian get to work with the power float to smooth them off. | Friday 12th SeptemberThe timber arrives and is arranged around the outside of the slab, however little if anything will happen next week as the joiners are finishing off the cladding for Dave & Gillian. |
|
| |
|