Monday 15th DecemberA great team effort by Brian (leveller), Gus (uppstairs bucket), Johnathan (downstairs bucket & wheel barrow) & Shug (mixer) to get both upper floors screeded in the day! | Tuesday 16th DecemberThe floor screed is setting well and Jerry completes the ground floor wiring in both houses. |
|
Wednesday 17th DecemberSpend the morning lifting 'Daves Dome' into position at the Old Barns, but still enough time for Jerry & the Joiners (nice name for a band?) to fit the gutters in place to protect Brian when he starts on the block work. | Thursday 18th DecemberGus & Jerry fit the chipboard floor to No.5 and half finish the same next door. Will finish off tomorrow and then holidays for 2 weeks! |
|
Friday 19th DecemberAngus & Jerry finish laying the chipboard floors in both houses while Joan coats the pre-cast corner stones with waterproof sealant. We then have a big clean-up and stop for a very well-earned 2 week break. | |
|