Monday 2nd MarchBrian & Shug build up the chimney on No.6, followd by more blocks at the rear of the building. The decorators paint No.5 and Jerry makes a start on the plumbing pipes in No.6. | Tuesday 3rd MarchNo inside work today, but the builders make good progress and manage to fit the first of the two chimney pots on No.6. |
|
Wednesday 4th MarchBrian makes a start on the scratch coat on the wall outside the back door of No.5. | Thursday 5th MarchMore heavy snow stops the builders today, but Jerry manages to finish the hot & cold water pipes in No.6. - this is the upstairs airing cupboard which houses the distrbution manifolds for the front of the house (Bathroom & Shower Room). |
|
Friday 6th MarchJerry completes the hidden wiring for the heating system, mounts the control boxes and finishes wiring-up the consumer unit. Everything is now ready for the tiler (Neil) to come in on Monday morning and start on the kitchen floor. | Friday 6th MarchMeanwhile the builders add more blocks & cills and scratch-coat a second wall. |
|
| |
|