Week 32 - All Sorts of Things
This will be a busy week on site as we expect to finish the external building work on the houses, clear away all the scaffolding in readiness for the groundworks to start next week, start the joinery finishing in No.6, start the electrical 2nd fix in No.5 and finally say goodbye to our site hut!
Monday 30th MarchThe builders complete the harling - just before the scaffolding is pulled down! | Monday 30th MarchThe scaffolding is cleared away from the front and sides of the bulding and the harling is getter whiter by the day, contrasting against the black rainwater pipes that Jonathan fitted. Inside Gus starts hanging the doors in No.6 and Jerry makes a start on the electrical 2nd fix in No.5. | | Tuesday 31st MarchGus finish hanging the doors downstairs in No.6 - the glazed doors into the hall look really nice. | Tuesday 31st MarchThe outside is looking great as well, particularly now the scaffolding is down. Jerry and John have a good day and complete the upper floor lighting & power circuits. | | | | |
|