Monday 12th JanuaryOutside Brian & Shug make good progress with the blockwork, including laying the first of the pre-cast corner stones. | Monday 12th JanuaryMeanwhile inside the joiners turn their hand to some plumbing work and the waste pipes are installed in both houses. |
|
Tuesday 13th JanuaryBrian collects a mini digger and prepares the heat pump slabs ready for concreting tomorrow. | Tuesday 13th JanuaryThe heating pipes and ducting as they leave the rear of the houses. We also took delivery of 216 sheets of plasterboard, 120 2" x 1" battens and 80 lengths of 3" x 2" studs for the internal partition walls. All this was successfully moved inside the houses before the end of the day! |
|
Wednesday 14th JanuaryShug screeds the heat pump slabs as Brian continues with the blocks and the joiners finish off the rigid insulation in No.5. | Thursday 15th JanuaryScaffolding is moved away from the house to give the builders better access to the walls, and at the same time the boards are dropped a level. |
|
Thursday 15th JanuaryShug digs the trenches for the pipes to the heat pump. | Friday 16th JanuaryThe builders make good progress - this is the internal corner of No. 5. Also, the heat pump pipes and conduit are back filled and levelled. |
|
Friday 16th JanuaryInside, Gus and Johnathan just about finish the strapping over the insulation in No. 5. | |
|