Monday 27th AprilJerry & Jonathan install the plumbing in the service cupboard & bathroom in No.5. | Tuesday 28th AprilWork on fitting out the bathroom continues. |
|
Tuesday 28th AprilThe kerbing has turned the corner and is now in front of the two houses. Jonathan offers some words of advice and encouragement to Larry. | Wednesday 29th AprilJohn & Gavin return to back-fill the hole for the water connections and re-tar the road. |
|
Wednesday 29th AprilThe kerbs for the access road and car parking slots are almost complete. | Wednesday 29th AprilLarry & Gary start laying the Geogrid blocks (which arrived last evening) in the car parking area. |
|
Thursday 30th AprilJerry wires up the second heat pump while Jonathan finishes the domestic plumbing (utility room in No.5) and Chris David attends to finalising the manifold plumbing prior to Earthwise returning on Monday to commission the heating system. | Thursday 30th AprilThe landscaping makes great progress with 2 of the four parking spaces now 'geogrided' and filled with top soil, and we also take delivery of our first lorry load of gravel for the roads. |
|
Friday 1st MayGus & Kevin return to make a start on the doors in No.5 while Jonathan works on the flooring. | |
|
| |
|
| |
|