Monday 25th AugustA much better day and the builders return to check the profiles, distribute the blocks around the site and layout the corners of the building. | Tuesday 26th AugustProgress on the blocks - 7 of the 8 corners are double skinned - just need to join up the gaps tomorrow. |
|
Wednesday 27th AugustBlockwork up to 2 courses - this will be the party wall between the 2 houses. | Thursday 28th AugustThree courses almost all the way round. Should be nearly finished by tomorrow evening although we will almost certainly need more blocks. |
|
Friday 29th AugustThe blockwork underbuilding nears completion - just a single layer of blocks on the inside to go which will have to wait until Tuesday as we are short of materials and can't get a delivery until then. | Friday 29th AugustShug keeps a close eye on the mixer! |
|
Friday 29th AugustMeanwhile, Brian keeps on using up all the cement. | |
|