Monday 11th MayThe heating systems are up and running so Jerry tidies up the wiring in the cupboards. | Monday 11th MayBrian points up the inner side of the front wall. |
|
Tuesday 12th MayThe first log burner is moved into its final position now that the tiling and grouting has been completed. Also the decorators make a start on the painting in No.6. | Tuesday 12th MayA significant moment as the lamp post is re-erected at the entrance to Nicol Terrace. Brian start building the wall at the other side of the entrance and we get the electrical work approved today (thanks to Stuart from JM Campbell). |
|
Wednesday 13th MayThe slabs reach the back door of No.6 - this shows a gentle ramp (1:20) from the pavement to the flat slab at the door. | Wednesday 13th MayThe painters apply the final coat of varnish to the doors in No.6 and we get the electrics approved & signed off for both houses. |
|
Thursday 14th MayWe welcome Gordon to site - initially he will be tiling the shower room & bathroom in No.6 (ready for completion in a couple weeks we hope). | Thursday 14th MayGus & Kevin return to move the finishing joinery on - Gus sets about the surround for the fireplace. |
|
Friday 15th MayThe access road takes shape with the addition of the pavior transition between the tarred bell mouth and the gravel road. | Friday 15th MayNow that the heating system has been commissioned the staircases can be fully enclosed ready for decorating. |
|
| |
|