Monday 23rd MarchBrian & Shug continue with the harling - today outside the back door of No. 5. Also the roofers return to complete their work by closing off around the last chimney. | Tuesday 24th MarchJerry makes a start on the second fix electrics in No. 5. |
|
Tuesday 24th MarchThe walls around the back door of No. 6 are now finished and Jerry also manages to put a final coat of varnish on some of the soffit and fascia boards. | Wednesday 25th MarchA big days work outside as Brian & Shug are joined by Tom and they firstly complete the harling of the gable end of No.6. |
|
Wednesday 25th MarchAnd then they do the same to the opposite wall on No.5. Just the back gables to go and the scaffold can come down! | Thursday 26th MarchAngus fits the kitchen worktops and cuts and glues the cornice pieces above and below the cabinets. |
|
Thursday 26th MarchJonathan completes the loft insulation and fits the sun pipe, while Jerry paints a final coat of stain on the remaining soffits and fascias. | Friday 27th MarchThe kitchen takes shape with the appliances (oven, hob, fridge/freezer and dishwasher) fully fitted and doors & handles in place. |
|
| |
|