Monday 26th JanuaryDespite an early finish to go to the dentist, the joiners make a good start on the plasterboard upstairs in No.6. | Monday 26th JanuaryIt was a very busy day on site! Contractors closed Church Street to work on the Barns services connection (using our entrance for their spoil); street lighting engineers dug up the same entrance to re-make the faulty temporary junction which had fused all the street lights in the vicinity; a decorating contractor came to assess our job and we took delivery of two very tall crates containing the Calorex air source heat pumps - courtesy of a very skillful and obliging JBT delivery driver. Hoping to get on with some real work tomorrow! |
|
Tuesday 27th JanuaryBrian gets the blockwork up and over the lintels (working off the scaffold 'hop-ups'). | Tuesday 27th JanuaryInside, the outside walls & ceiling upstairs in No.6 are almost finished. |
|
Wednesday 28th JanuaryBlock work well over lintels at the front. We also finally managed to fit the register plates (900 x 600 slab with 100 mm hole through it) so Brian can now set about building the chimneys. | Wednesday 28th JanuaryDownstairs ceilings plasterboarded and a start made on the walls in the lounge of No.6. |
|
Thursday 29th JanuaryJonathan fits the last sheets to the outside wall of No.6 - the bathroom and shower rooms are lined with plywood to allow handrails to be securely fitted in future, if required. | Friday 30th JanuaryThe joiners finish plasterboarding upstairs in No. 6 |
|
| |
|