Monday 11th AugustA fine day for the start. Brian, Hugh and Gus mark out the site before the digger arrives to 'scrape' it level. | Monday 11th AugustAn aerial view of the site after the base has been scraped but before the spoil is removed. |
|
Tuesday 12th AugustA bit of a frustrating day mainly spent waiting for the trailer to return after taking a load of earth away. Still at the end of it we have a flat, level site ready for digging the foundation trenches tomorrow. | Wednesday 13th AugustJamie and his digger get to work on the foundation trenches. |
|
Wednesday 13th AugustThe trenches mid-morning ... | Wednesday 13th August... and later in the day. |
|
Thursday 14th AugustFoundation trenches completed, ready for concrete to be poured Monday morning. | |
|