Monday 5th JanuaryHappy New Year! Back to work and spend the day adding the circuits for the heating system and the hot water cylinder and buffer tank immersion heaters in No. 6. The joiners and builders are away preparing the Old Barns upper floor for screeding. | Tuesday 6th JanuaryMost of the day spent on the upper floor lighting wiring in No. 6 whilst the joiners & builders screed the Old Barns. |
|
Wednesday 7th JanuaryFitted the loft ladder in No. 6 and finished off the upper floor lighting circuits. | Wednesday 7th JanuaryThe joiners return and make a start on fitting the rigid insulation to the coombes and ceilings. |
|
Tursday 8th JanuaryThe builders make a start on the exterior blockwork. | Friday 9th JanuaryThe Old Barns floor is finally finished so the joiners start fitting the 2" x 1" straps on the upper floor of No. 6. |
|
Friday 9th JanuaryThe upper floor is taking shape. | |
|