Monday 27th OctoberWe start by loading some sarking boards onto the scaffolding. | Monday 27th OctoberGus & Jonothan start sarking the long roof at the front while Jerry attends to 100 assorted bolts and brackets on the multiple roof trusses. |
|
Tuesday 28th OctoberDespite awful weather (snow and sleet for most of the day) we finish the front roof and make a start on the back. | Wednesday 29th OctoberSince the clocks changed we seem to have late finishes (spot the joiner in the fluorescent jacket). |
|
Wednesday 29th OctoberGus completes the rafter trusses (bits to carry the small roof onto the large roof) and we add more sarking boards. A good day tomorrow and we should be about finished with them!! | Thursday 30th OctoberA 'bitty' day as Angus is called away to the Old Barn, but he still has time to complete the fire proof wall between the two houses on his return. |
|
Thursday 30th OctoberAnd by the end of the day the sarking is almost completed on both houses. | Friday 31st OctoberAll roof sarking finished and most of the breathable membrane covering fitted (until we ran out of material). We also started framing the dormer windows before an early finish. |
|
| |
|