Monday 29th SeptemberFloor joists completed on one house. | Tuesday 30th SeptemberSecond house joisted out and both houses fully 'dwanged' so we can start on the upper floor tomorrow. |
|
Wednesday 1st OctoberDespite some showers we make good progress in covering the floor joists with 10mm plywood, which now gives us some protection downstairs. | Wednesday 1st OctoberBy the end of the day both houses have been covered and the ring binder for the upper floor panels has been fixed in place. |
|
Thursday 2nd OctoberA day of sporadic heavy rain but we still manage to mark out the ring binders and make up 10 panels for the upper floor, as well as take delivery of yet more timber for the roof and walls. | Friday 3rd OctoberWe make up the two large gable panels (with central window) remembering to reduce the overall height to allow for the gable ladder. |
|
| |
|