+ Let there be wind

Pen y Cymoedd Wind Energy Project

Vattenfall of Cardiff  reports the following news 

Since November 2015 we have delivered up to six turbine component deliveries to site per day (Monday to Saturday) in two convoys.

With 684 abnormal loads in total this has been a huge operation. The unpredictable weather has meant that many deliveries have had to be rescheduled for safety reasons.

We are now nearing the end of the turbine component deliveries and expect them to be completed by the middle of October.

We would like to thank you for your patience, especially if you have happened to get stuck behind one of our convoys. 

Mike Davies has produced us with over 530 images  since Nov of 2015 without including video content

Photographs of our deliveries can be viewed courtesy of Mike Davies

Report by Emily Faull Vattenfall’s local project officer for Pen y Cymoedd

Flickr images and YouTube images content courtesy by Mike Davies

https://www.flickr.com/photos/120047838@N03/sets/72157666906386593

You tube link here https://www.youtube.com/watch?v=Y1Wrhk6MiYc

If the above links are not active, copy and paste them in your browser

 

+ Readers write about the Windmills - see Readers Letters

 

 

 

Click for Map
sitemap | cookie policy | privacy policy | accessibility statement