Pen y Cymoedd Wind Energy Project
Vattenfall of Cardiff reports the following news
Since November 2015 we have delivered up to six turbine component deliveries to site per day (Monday to Saturday) in two convoys.
With 684 abnormal loads in total this has been a huge operation. The unpredictable weather has meant that many deliveries have had to be rescheduled for safety reasons.
We are now nearing the end of the turbine component deliveries and expect them to be completed by the middle of October.
We would like to thank you for your patience, especially if you have happened to get stuck behind one of our convoys.
Mike Davies has produced us with over 530 images since Nov of 2015 without including video content
Photographs of our deliveries can be viewed courtesy of Mike Davies
Report by Emily Faull Vattenfall’s local project officer for Pen y Cymoedd
Flickr images and YouTube images content courtesy by Mike Davies
https://www.flickr.com/photos/120047838@N03/sets/72157666906386593
You tube link here https://www.youtube.com/watch?v=Y1Wrhk6MiYc