 Monday 13th Feb Foundation walls started by Bennie with Jerry labouring!
|
|
 Tuesday 14th Feb Foundation walls make good progress.
|
|
 Wednesday 15th Feb Foundation blockwork complete.
|
|
 Friday 17th Feb Swimming Pool crates delivered to site from their temporary home at Cyderhall Farm. We are grateful to Donald & Alan Munro for their help in transporting and storing the pool for us. The crates are now wrapped in polythene to protect them from the elements and are standing on the slabs outside the back door.
|
|
 Friday 17th Feb Swimming Pool crates delivered to site from their temporary home at Cyderhall Farm (grateful thanks to Donald & Allan Munro for all their help). |
|
 Friday 17th Feb The crates are wrapped in polythene to protect them from the elements and are standing on the slabs outside the back door.
Also, we (thanks Dad!) moved about 400 4" blocks by hand from the front of the site to allow access for the timber frame kit!
|
|
| |