 Sunday 26th Feb Trenching of the electric cable is almost completed, but we struck stone underneath the paving slabs (hence the pick axe)! |
|
 Monday 27th Feb Trusses arrive and are stored on the neighbour's lawn! |
|
 Wednesday 1st March The kit arrived at 7.30 a.m. today. Unfortunately the snow beat it by 24 hours and so far we have about 4 inches covering the site! |
|
 Wednesday 1st March However, after a lot of shovelling and gritting (not to mention slipping & sliding) the driver left the trailer on the neighbour's lawn - again! |
|
 Thursday 2nd March Despite more snow overnight (about 6 inches now) the Norscot team arrived from Caithness early this morning and started work on the timber frame kit. |
|
 Thursday 2nd March By the end of the day all the external walls of the kit were in place. A great days work! Roll on tomorrow when, hopefully, the roof trusses will go up. |
|
 Friday 3rd March Yet more snow but a 7 a.m. start with our shovels enabled the trailer to be collected and the guys make good progress again. |
|
 Friday 3rd March At the end of the week the internal wall and roof trusses are in place and the facia boards have been started. |
|
| |