 Monday 22nd May Installed the stainless steel benches around the sides of the pool. |
|
 Monday 22nd May Continue filling with water up to about 2' depth - fills at about 3" per hour! |
|
 Monday 22nd May Meanwhile we finish varnishing the side panels and start the decking floor. |
|
 Tuesday 23rd May Bennie returns to complete the external rendering. |
|
 Tuesday 23rd May By the end of the day the outside walls are complete. Just some finishing touches required now (a wall, paving slabs etc.). |
|
 Wednesday 24th May Completed the plumbing at the front of the pool and finished filling with water. |
|
 Thursday 25th May Cut and laid the decking floor ready for screwing down tomorrow - when (hopefully) the electrician will connect the power and we can get going!! |
|
 Saturday 27th May After a 24 hour settling in period the water is up to temperature (78°) and we have our first swim! The end. |
|
| |