 Monday 6th March By lunchtime we have a roof, window and door-set. |
|
 Monday 6th March And by evening everything else is in place. All that is left is to complete the hanging of the garage door tomorrow. |
|
 Tuesday 7th March Norscot have completed their work and the roofers fitted the tile battens this afternoon, but in a change of plan we will start to build-up the end walls tomorrow. |
|
 Wednesday 8th March The exterior blockwork on the gable ends is started. |
|
 Wednesday 8th March At the same time the roof is loaded with tiles in readiness for fitting next week. |
|
 Thursday 9th March Bennie's blockwork reaches lintel level. |
|
 Friday 10th March Large lintel in place and gable-end blockwork completed so we can start on the roof on Monday. |
|
| |